Home | favorite | site map order hotline:86 371 67996718
 

 

Current location:Henan ZhongKe Engineering&Technology Co.,Ltd >> Product >> crusher >> 浏览文章

Crusher Operation and Maintenance


点此在新窗口浏览图片

 

Crusher Operation and Maintenance

I,The test run in the first : crusher trail operation , must strictly according to the following before program examination .

1,Spindle bearings , transmission shaft bearing grease injection .

2,Crushing cavity (including BiZi above) whether more exotic foreign bodies .

3,Crusher rotor disc car check , eliminate metal clash .

4,Each component bolt and the anchor bolts are tight .

5,Motor rotation direction is correct .

6,Whether all the door body already firmly closed .

II,No load test : before shall first no-load test according to the relevant rules for electrical professional main motor testing .Then on the main motor racing test , without exception , criterion for eight hours of no load test , and meet the following requrements .

1,The start-up time of main motor shall not exceed 35s .

2,No metal hitting and running voice .

3,The rotor smooth operation .

4, Spindle bearing temperature usually less than 78 ℃.

5,The main motor current smoothly .

6,After stopping during operation ,check each copy bolts and pin , and screw down loose bolts .

7,Stop time (from the main motor to rotor complete stop) less than 20 min .

III,Load test : no load test , just can have qualified load test after the class , load test running time generally not less than 6h , and should press the following requirements .

1,Before connecting bolts review all running strong the anchor bolt .

2,Crusher must empty load startup . Startup sequence should be first crusher below the tape transporters ,then start crusher .Crusher to normal speed ,and then start board feeding machine join ore , parking procedures and to the contrary . Rotar and the feeding machine stop gap each remaining ore row within all shall prevail .

3,Load test 1/2 lotus small pieces , half load mediummaterials ,full load normal three steps .

IV,Note :

1,The machine for the fully closed discharging BiaZi , so production should strive to avoid iron piece of hard to break into the machine , lest in foreign to grate bars parts damage .

2,Excessive ore should not enter into the crusher .

3, Note the voice of monitor machine, if discovery is unusual voice, immediately stop check, find out the reason and deal with failure, can continue to work .

4, , the main bearing and high-speed shaft housings equipped with the measuring range – 100 ~ 100 ℃ WZPM - 201BA2 type of thermal resistance, as bearing temperature transmitter, and equipped with alarm device. When the temperature more than 85 ℃, the temperature in the cap on alarm device, will adjust) issued a warning signal to 90 ℃, the temperature will stop working automatically. Bearing can withstand ℃ temperature of 100 avoid damage .

5,The main bearing (rotor bearing) and high speed shaft bearings (small pulleys bearing) adopts grease-lubricated, use of high quality lithium base fat, grease should change regularly.

Add : maintenance special instructions

1, Hammer: hammer in use process gradually to reduce wear, hammer heavy about 80%, otherwise production must be replaced, grain size, are difficult to ensure new hammer front edge grinding to the edges of the width of the 3/5, can hammer flanging use.

2, , hammer shaft: use after a long period of hammer axis. Usually in hang hammerheads place and hammer dish support place be ground grooved, produce arris edge, in reinstall this hammer before by burnish, axial run flat eliminate these edges or edge, to improve the hammer shaft bearing conditions.

3,When in normal conditions, the yield increased or reduced, power the grain-size coarsens, should check hammer BiZi and other components, and the abrasion of adjustment and maintenance.

4,This machine formally put into use, spindle bearing one time, should run clean bearing replacement fat once, to ensure bearing normal work and service life.

5,Crusher, adopted in running over load and short circuit protection, gives the ore machine with crusher load change quantificationally feeding and automatic adjustment, the broken system implement electrical interlocking.

Last:Portable Crushing Screening Station

Next:Mobile Crushing & Screening Plant - The New Choice for Surface Coal Mining

hnzkmachinery@hotmail.com MSN chat online Contact us


solar panel|Crusher|Brick Making Machine|Block Machine|Crushing Equipment|quarry plant|steel shaft Ball Mill|Grinding Mill

crushing equipment/mobile crushing plant/sand making machine/beneficiation equipment/stone crusher/rotary dryer/grinding mills

Address:Zhengzhou high-tech development zone, Henan, China Tel:0086-371-67996718

Fax: 0086-371-67103886 mobile phone:0086-(0)13838093345 E-mail:hnzkmachinery@hotmail.com